IP Library Granted Patent US 11,525,941
Granted Patent B2
US 11,525,941 · App. 16/957,009 · Granted Dec 13, 2022

In-situ calibration of borehole gravimeters

Inventors: Paul F. Rodney (Spring, TX); Daniel Joshua Stark (Houston, TX)
Assignee: Halliburton Energy Services, Inc.
G01V13/00E21B23/00E21B47/12G01V7/02E21B49/00
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,525,941
App. No.
16/957,009
Granted
Dec 13, 2022
Kind
B2
Abstract

A method and system for in-sit calibration of a gravimeter. A method may comprise disposing a downhole tool in a borehole, wherein the downhole tool comprises the gravimeter attached to a linear actuator, recording a first set of measurements with the gravimeter while the linear actuator is stationary, activating the linear actuator, recording a second set of measurements with the gravimeter, and calibrating the gravimeter based on the first and second set of recorded measurements. A system may comprise a downhole tool, a conveyance, and an information handling system. The downhole tool may further comprise a hanger, a sonde, connected to the hanger, a linear actuator, connected to the hanger, and a shaft, connected to the linear actuator. The downhole tool may further comprise a linkage, connected to the shaft, a package, connected to the linkage, and a gravimeter, disposed in the package.

Claims (43)

1. A method for in-situ calibration of a gravimeter, comprising:

disposing a downhole tool in a borehole, wherein the downhole tool comprises the gravimeter attached to a linear actuator, wherein the linear actuator is configured to drive axial movement of the gravimeter, and wherein the downhole tool further comprises a plurality of springs configured to restrain lateral movement of the gravimeter;

recording a first set of measurements with the gravimeter while the linear actuator is stationary;

activating the linear actuator to cause the gravimeter to move axially;

recording a second set of measurements with the gravimeter; and

calibrating the gravimeter based on the first and second set of recorded measurements.

2. The method of claim 1 , further comprising activating an acceleration sequence for the linear actuator in an analog mode.

3. The method of claim 2 , further comprising producing waveforms for the analog mode and energizing the linear actuator using the waveforms.

4. The method of claim 3 , further comprising sending confirmation to the information handling system that the acceleration sequence is complete.

5. The method of claim 1 , further comprising activating an acceleration sequence for the linear actuator in a stepper mode.

6. The method of claim 5 , further comprising producing a series and timing command for the stepper mode and energizing the linear actuator using the series and timing command.

7. The method of claim 6 , further comprising sending confirmation to the information handling system that the acceleration sequence is complete.

8. The method of claim 1 , wherein the recording a first set of measurements with the gravimeter while the linear actuator is stationary comprises a time delay to allow the gravimeter to be powered and stabilized.

9. The method of claim 1 , further comprising specifying a calibration parameter.

10. The method of claim 9 , wherein the calibration parameter is a number of constant acceleration intervals, a magnitude and sign of acceleration for each interval, an acceleration sample rate, or an acceleration to be produced in an analog mode or a stepper mode.

11. The method of claim 1 , further comprising rotating the gravimeter and measuring a bias.

12. A system comprising:

a downhole tool, wherein the downhole tool comprises:

a hanger;

a sonde connected to the hanger;

a linear actuator disposed within the sonde and having a proximal end connected to the hanger;

a shaft extending from a distal end of the linear actuator;

a package connected to the shaft via a linkage, wherein activating the linear actuator is configured to extend and retract the shaft along a central axis of the sonde to drive axial movement of the package;

a gravimeter disposed in the package such that axial movement of the package moves the gravimeter axially; and

a plurality of springs disposed within the sonde and configured to restrain lateral movement of the package such that lateral movement of the gravimeter is restrained;

a conveyance attached to the downhole tool; and

an information handling system, wherein the information handling system is in signal communication with the downhole tool, and configured to initiate a calibration sequence, send commands to a linear actuator module and a gravimeter module, record a first set of measurements while the linear actuator is stationary; activate the linear actuator; record a second set of measurement while the linear actuator is moving; calibrate the gravimeter based on the first and second set of recorded measurements; and store the calibration results.

13. The system of claim 12 , wherein the information handling system is configured to activate an acceleration sequence for the linear actuator in an analog mode.

14. The system of claim 13 , wherein the information handling system is configured to produce waveforms for the analog mode and energizing the linear actuator using the waveforms.

15. The system of claim 14 , wherein the information handling system is configured to send confirmation to the information handling system that the acceleration sequence is complete.

16. The system of claim 12 , wherein the information handling system is configured to activate an acceleration sequence for the linear actuator in a stepper mode.

17. The system of claim 16 , wherein the information handling system is configured to produce a series and timing command for the stepper mode and energizing the linear actuator using the series and timing command.

18. The system of claim 17 , wherein the information handling system is configured to send confirmation to the information handling system that the acceleration sequence is complete.

19. The system of claim 12 , wherein gravimeter is a three axis gravimeter.

20. The system of claim 12 , further comprising a plurality of gravimeters.

21. A downhole tool, wherein the downhole tool comprises:

a hanger;

a sonde connected to the hanger;

a linear actuator disposed within the sonde and having a proximal end connected to the hanger;

a shaft extending from a distal end of the linear actuator;

a package connected to the shaft via a linkage, wherein activating the linear actuator is configured to extend and retract the shaft along a central axis of the sonde to drive axial movement of the package; and

a gravimeter disposed in the package such that axial movement of the package moves the gravimeter axially;

a plurality of springs disposed within the sonde and configured to restrain lateral movement of the package such that lateral movement of the gravimeter is restrained.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 23, 2020
From: RODNEY, PAUL F.; STARK, DANIEL JOSHUA
To: HALLIBURTON ENERGY SERVICES, INC.
Reel/Frame 053009/0942 →
Continuity (1)
Related Publication 20210041595A1 · Feb 11, 2021