Process for workover of a well for a hydrocarbon recovery operation

Inventor: Desmond Larry Procinsky (Calgary, CA)
Assignee: Cenovus Energy Inc.
E21B43/24E21B43/34
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,163,408
App. No.
18/225,632
Granted
Dec 10, 2024
Kind
B2
Abstract

A process for workover of a hydrocarbon recovery well, wherein hydrocarbons are mobilized and well pressure increased by steam injection, the hydrocarbons produced to surface in emulsion fluids. The emulsion fluids are directed into a produced emulsion line at surface at a first pressure, steam injection is then discontinued into the well while continuing emulsion production at reduced pressure, at least some of the emulsion fluids are redirected to an additional line at a second pressure lower than the first pressure as pressure in the well decreases, the emulsion fluids are pumped from the additional line into the produced emulsion line at a third pressure higher than the second pressure, and a well kill fluid is injected into the well to allow the workover after the well pressure decreases.

Claims (13)

1. A process for workover of a well utilized in recovery of hydrocarbons from a subterranean hydrocarbon formation, comprising:

injecting steam into the well and into the formation to mobilize a portion of the hydrocarbons in the formation and increase pressure in the well;

producing emulsion fluids comprising the portion of the hydrocarbons from the formation through the well to surface, thus decreasing the pressure in the well, and directing the emulsion fluids into a produced emulsion line at the surface operating at a first pressure for separation at a facility;

discontinuing the injecting of the steam into the well while continuing the producing of the emulsion fluids at a reduced pressure to the surface;

discontinuing directing at least a portion of the emulsion fluids to the produced emulsion line and instead directing the at least a portion of the emulsion fluids to an additional line at the surface, the additional line operating at a second pressure lower than the first pressure, as pressure in the well decreases;

pumping the at least a portion of the emulsion fluids from the additional line at a third pressure higher than the second pressure into the produced emulsion line for separation of the portion of the hydrocarbons from the emulsion fluids at the facility; and

injecting a well kill fluid into the well and beginning the workover of the well after the pressure in the well decreases.

2. The process according to the claim 1 , wherein the injecting of the steam into the well and into the formation and the producing of the emulsion fluids from the formation are carried out in a start-up phase of operation.

3. The process according to claim 2 , wherein the workover of the well comprises preparing for a production phase of operation after the start-up phase of operation.

4. The process according to claim 1 , wherein the pumping of the at least a portion of the emulsion fluids comprises pumping utilizing a progressive cavity pump to direct the at least a portion of the emulsion fluids into the produced emulsion line for separation.

5. The process according to claim 1 , wherein the additional line comprises a test line and directing the at least a portion of the emulsion fluids to the additional line comprises directing the at least a portion of the emulsion fluids to the test line as the pressure in the well decreases.

6. The process according to claim 1 , wherein the pressure in the well is decreased from an initial pressure in a range of 2500 kPa to 3200 kPa.

7. The process according to claim 1 , wherein the produced emulsion line is coupled to a plurality of wells that include the well, wherein the produced emulsion line is configured to receive the emulsion fluids from the plurality of wells.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Sep 27, 2023
From: PROCINSKY, DESMOND LARRY
To: CENOVUS ENERGY INC.
Reel/Frame 065049/0939 →
Continuity (3)
Division 17574425 · Jan 12, 2022
Provisional Application 63138158 · Jan 15, 2021