Systems and processes for generating electricity from a geothermal energy source via an integrated thermal power plant

Inventor: Babak Bob Arefi (Spring, TX)
F03G4/029F03G4/033F24T10/13F24T50/00F24T2010/50
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,320,339
App. No.
18/294,910
Granted
Jun 3, 2025
Kind
B2
Abstract

Geothermal energy systems and processes eliminate or reduce the distance between a geothermal energy source and an electricity generating power plant The systems and processes include heating a primary fluid by absorbing thermal energy from the geothermal energy source in a well to produce a heated primary fluid; conveying the heated primary fluid to the power plant including, a turbine and an electricity generator; driving the turbine by one of: the heated primary fluid; and a secondary fluid that absorbs thermal energy from the heated primary fluid via, a heat exchanger; and driving the electricity generator via, the turbine to generate electricity. The power plant is positioned at one of: inside the well; partially inside the well; at a wellhead above the well; adjacent to the well; on a pad including one or more wells; and between multiple pads including one or more wells in the same field of pads.

Claims (48)

1. A process of generating electricity from a geothermal energy source, comprising:

heating a primary fluid by absorbing thermal energy from the geothermal energy source in a well to produce a heated primary fluid;

conveying the heated primary fluid to a thermal power plant that comprises a turbine and an electricity generator, wherein the turbine comprises a device or equipment that transfers kinetic energy to mechanical energy to perform work;

driving the turbine by one of: the heated primary fluid; and a secondary fluid that absorbs thermal energy from the heated primary fluid via a heat exchanger; and

driving the electricity generator via the turbine to generate electricity, wherein:

the turbine and the electricity generator are positioned at one of: inside the well; partially inside the well; and at a wellhead above the well; and

the turbine and the electricity generator are maintained in position via an attachment to the wellhead.

2. The process according to claim 1 , further comprising extracting heat from one of the heated primary fluid and the secondary fluid that exits the turbine in a condenser to reduce a temperature of the one of the heated primary fluid and the secondary fluid.

3. The process according to claim 1 , further comprising increasing a pressure of the one of the heated primary fluid and the secondary fluid via one of: (i) a compressor when the one of the heated primary fluid and the secondary fluid is in a gaseous phase; and (ii) a pump when the one of the heated primary fluid and the secondary fluid is in a liquid phase.

4. The process according to claim 1 , wherein the one of the heated primary fluid and the secondary fluid changes to a supercritical state or a gaseous state when absorbing thermal energy, and wherein the turbine and the electricity generator are positioned at a predetermined distance from the geothermal energy source to maintain the supercritical state or the gaseous state so that the one of the heated primary fluid and the secondary fluid enters the turbine in the supercritical state or the gaseous state.

5. A geothermal system for generating electricity, comprising:

a well that comprises a geothermal energy source;

a primary fluid that absorbs thermal energy from the geothermal energy source to produce a heated primary fluid; and

a thermal power plant comprising a turbine and an electricity generator, wherein the turbine comprises a device or equipment that transfers kinetic energy to mechanical energy to perform work, and wherein:

the turbine is driven by one of: the heated primary fluid; and a secondary fluid that absorbs thermal energy from the heated primary fluid via a heat exchanger;

the electricity generator is driven by the turbine to generate electricity;

the turbine and the electricity generator are positioned at one of: inside the well; partially inside the well; and at a wellhead above the well; and

the turbine and the electricity generator are maintained in position via an attachment to the wellhead.

6. The geothermal system according to claim 5 , further comprising a condenser that extracts heat from one of the heated primary fluid and the secondary fluid that exits the turbine to reduce a temperature of the one of the heated primary working fluid and the secondary fluid.

7. The geothermal system according to claim 5 , further comprising one of:

(i) a compressor to increase a pressure of the one of the heated primary fluid and the secondary fluid when the one of the heated primary fluid and the secondary fluid is in a gaseous phase; and

(ii) a pump to increase a pressure of the one of the heated primary fluid and the secondary fluid when the one of the heated primary fluid and the secondary fluid is in a liquid phase.

8. The geothermal system according to claim 5 , wherein the one of the heated primary fluid and the secondary fluid changes to a supercritical state or a gaseous state when absorbing thermal energy, and wherein the turbine and the electricity generator are positioned at a predetermined distance from the geothermal energy source to maintain the supercritical state or the gaseous state so that the one of the heated primary fluid and the secondary fluid enters the turbine in the supercritical state or the gaseous state.

9. A geothermal system for generating electricity, comprising:

a pad;

a plurality of producing wells on the pad, wherein each of the producing wells comprises a geothermal energy source, and wherein each of the producing wells includes a primary fluid that absorbs thermal energy from the geothermal energy source to produce a heated primary fluid; and

a plurality of thermal power plants each comprising a turbine and an electricity generator, wherein the turbine of each of the thermal power plants comprises a device or equipment that transfers kinetic energy to mechanical energy to perform work, wherein:

each of the thermal power plants receives the heated primary fluid from a corresponding one of the producing wells on the pad or the multiple pads;

the turbine and the electricity generator of each of the thermal power plants are positioned:

inside of a corresponding one of the producing wells;

partially inside of a corresponding one of the producing wells; and

at a wellhead above a corresponding one of the producing wells; and

the turbine and the electricity generator of each of the thermal power plants are maintained in position via an attachment to the wellhead.

10. The geothermal system according to claim 9 , wherein, for each of the thermal power plants:

the turbine is driven by one of: the heated primary fluid; and a secondary fluid that absorbs thermal energy from the heated primary fluid via a heat exchanger; and

the electricity generator is driven by the turbine to generate electricity.

11. The geothermal system according to claim 10 , wherein each of the thermal power plants further comprises a condenser that extracts heat from one of the heated primary fluid and the secondary fluid that exits the turbine to reduce a temperature of the one of the heated primary working fluid and the secondary fluid.

12. The geothermal system according to claim 10 , wherein each of the thermal power plants further comprises one of:

(i) a compressor to increase a pressure of the one of the heated primary fluid and the secondary fluid when the one of the heated primary fluid and the secondary fluid is in a gaseous phase; and

(ii) a pump to increase a pressure of the one of the heated primary fluid and the secondary fluid when the one of the heated primary fluid and the secondary fluid is in a liquid phase.

13. The geothermal system according to claim 9 , wherein the one of the heated primary fluid and the secondary fluid changes to a supercritical state or a gaseous state when absorbing thermal energy, and wherein the turbine and the electricity generator of each of the thermal power plants is positioned at a predetermined distance from the geothermal energy source to maintain the supercritical state or the gaseous state so that the one of the heated primary fluid and the secondary fluid enters the turbine in the supercritical state or the gaseous state.

14. The process according to claim 1 , wherein the turbine and the electricity generator are positioned inside the well.

15. The process according to claim 1 , wherein the turbine and the electricity generator are positioned partially inside the well.

16. The process according to claim 1 , wherein the turbine and the electricity generator are positioned inside the wellhead above the well.

17. The geothermal system according to claim 5 , wherein the turbine and the electricity generator are positioned inside the well.

18. The geothermal system according to claim 5 , wherein the turbine and the electricity generator are positioned partially inside the well.

19. The geothermal system according to claim 5 , wherein the turbine and the electricity generator are positioned inside the wellhead above the well.

20. The geothermal system according to claim 9 , wherein the turbine and the electricity generator of each of the thermal power plants are positioned inside the wellhead above a corresponding one of the producing wells.

Continuity (2)
Provisional Application 63229810 · Aug 5, 2021
Related Publication 20240337254A1 · Oct 10, 2024
References Cited (10)
US 3908381A · Barber et al. · 1975 [cited by applicant]
US 6668554B1 · Brown · 2003 [cited by applicant]
US 20120174581A1 · Vaughan · 2012 [cited by examiner]
US 20130227947A1 · Bronicki · 2013 [cited by examiner]
US 20130333383A1 · Schwarck · 2013 [cited by examiner]
US 20180224164A1 · Lakic · 2018 [cited by applicant]
US 20200347707A1 · Bowdon et al. · 2020 [cited by applicant]
US 20230077091A1 · Arefi · 2023 [cited by examiner]
US 20240183342A1 · Taylor · 2024 [cited by examiner]
International Preliminary Report of Patentability (Chapter II of PCT App No. PCT/US2022/039592) Oct. 18, 2023. [cited by applicant]