Techniques for steering communication traffic of a user equipment in a wireless communication network

Inventor: Dieter Petermann (Bonn, DE)
Assignee: DEUTSCHE TELEKOM AG
H04W36/362H04W28/0231
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,526,718
App. No.
18/553,855
Granted
Jan 13, 2026
Kind
B2
Abstract

A method for steering communication traffic of a user equipment (UE) in a network includes network entities that are configured to provide a radio access network for the user equipment. A serving network entity provides a current access to the network for the UE. Each network entity communicates with neighboring network entities. An algorithm implemented on a network unit uses as input a first time duration (Tcell), when the UE is within a radio coverage of the serving network entity, and a second time duration (TLC) that is time taken by the network to determine an adjusted load control setting. If Tcell>TLC the algorithm applies load control procedures within the communication network, and transmits a Radio Resource Control message with a network-calculated load control information to the UE. Otherwise, the algorithm transmits a Radio Resource Control message without the network-calculated load control information to the UE.

Claims (52)

1 . A method for steering communication traffic of a user equipment (UE), in a wireless communication network,

wherein the wireless communication network comprises at least some base stations that are configured to provide a radio access network (RAN) for the UE, including a serving base station that provides current access to the wireless communication network for the UE,

wherein each of the base stations is configured to communicate at least with its neighboring base stations, and

wherein the method comprises:

using, by a base station of the at least some base stations, as a first input a first time duration T Cell , wherein T Cell estimates a time duration that the UE is within a radio coverage area of the serving base station;

using, by the base station, as a second input a second time duration T LC , wherein T LC estimates a time duration it takes the wireless communication network to determine an adjusted load control setting for the UE;

comparing, by the base station, T Cell against T LC ; and

when T Cell >T LC :

applying, by the base station, load control procedures within the wireless communication network;

adding, by the base station, a network-calculated load control information to a Radio Resource Control message; and

transmitting, by the base station, the Radio Resource Control message with the network-calculated load control information to the UE; or

when T Cell <T LC :

transmitting, by the base station, the Radio Resource Control message without the network-calculated load control information to the UE.

2 . The method of claim 1 , wherein when T Cell <T LC , the Radio Resource Control message is provided with network-mapped based load control information for the UE.

3 . The method according to claim 1 , wherein the base station of the at least some base stations is the serving base station.

4 . The method according to claim 3 , wherein the serving base station requests the status information from the UE.

5 . The method according to claim 1 , wherein T Cell is estimated based on status information of the UE.

6 . The method according to claim 1 , wherein T LC is estimated based on a status information exchange between the serving base station and its neighboring base stations.

7 . The method according to claim 6 , wherein the serving base station requests the respective status information of its neighboring base stations.

8 . The method according to claim 1 , wherein the network-calculated load control pieces of information and/or the network-mapped load control pieces of information are selected to be offset values, capacity values, load values or priority values characterizing each neighboring base station.

9 . The method according to claim 1 , wherein the comparison is performed by using T # LC instead of T LC , with T # LC =T LC +T safety , wherein T safety is a safety time interval.

10 . The method of claim 9 , wherein T safety is adapted dynamically according to a previous success rate.

11 . The method according to claim 1 , wherein the UE starts a Conditional Handover (CHO) process to connect to another base station based on the Radio Resource Control message when the UE detects a CHO condition.

12 . The method according to claim 1 , wherein the network-calculated and/or network-mapped load control information depends on a current application running on the UE.

13 . A wireless communication system comprising:

a wireless communication network;

a user equipment (UE) configured to connect to the wireless communication network and to exchange data with the wireless communication network;

at least some base stations configured to provide a radio access network (RAN) for the user equipment, including a serving base station configured to provide current access to the wireless communication network for the UE;

a wireless and/or wired communication link between the serving base station and its neighboring base stations; and

wherein a base station of the at least some base stations is configured to:

use as a first input a first time duration T Cell , wherein T Cell estimates a time duration that the UE is within a radio coverage area of the serving base station;

use as a second input a second time duration T LC , wherein T LC estimates a time duration it takes the wireless communication network to determine an adjusted load control setting for the UE;

compare T Cell against T LC ; and

when T Cell >T LC :

apply, by the base station, load control procedures within the wireless communication network;

add a network-calculated load control information to a Radio Resource Control message; and

transmit the Radio Resource Control message with the network-calculated load control information to the UE; or

when T Cell <T LC :

transmit the Radio Resource Control message without the network-calculated load control information to the UE.

14 . A base station, wherein the base station comprises:

a first communication interface to provide a radio access network (RAN) for a user equipment (UE);

a second communication interface to communicate in a wired or wireless fashion with further network entities; and

a processor configured to:

use as a first input a first time duration T Cell , wherein T Cell estimates a time duration that the UE is within a radio coverage area of a serving base station;

use as a second input a second time duration T LC , wherein T LC estimates a time duration it takes the wireless communication network to determine an adjusted load control setting for the UE;

compare T Cell against T LC ; and

when T Cell >T LC :

apply, by the base station, load control procedures within the wireless communication network;

add a network-calculated load control information to a Radio Resource Control message; and

transmit the Radio Resource Control message with the network-calculated load control information to the UE; or

when T Cell <T LC :

transmit the Radio Resource Control message without the network-calculated load control information to the UE.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 30, 2023
From: PETERMANN, DIETER
To: DEUTSCHE TELEKOM AG
Reel/Frame 065708/0388 →
Priority Claims (1)
EP 21168983 · Apr 16, 2021 · regional
Continuity (1)
Related Publication 20240187957A1 · Jun 6, 2024
References Cited (5)
US 20200065694A1 · Mohapatra et al. · 2020 [cited by applicant]
US 20200351725A1 · Kim et al. · 2020 [cited by applicant]
US 20210084528A1 · Kim et al. · 2021 [cited by applicant]
WO WO2019187302A1 · 2019 [cited by examiner]
Ericsson, “Mobility Settings Change procedure for NG RAN”, Feb. 24-Mar. 6, 2020 E-Meeting, vol. RAN WG3, No. E-Meeting Feb. 24, 2020-Mar. 6, 2020, par. 1, 2.1, 2.2, 2.3, 3 and 4, BNSDOCID: XP51854319A, 3GPP Draft; R3-20… [cited by applicant]