System of critical datacenters and behind-the-meter flexible datacenters

Inventors: Michael T. McNamara (Newport Beach, CA); David J. Henson (Houston, TX); Raymond E. Cline, Jr. (Houston, TX)
Assignee: LANCIUM LLC
H02J3/386G05B13/041G06F1/28H02J3/00H02J3/003H02J3/06H02J3/144H02J3/38H02J3/383H02J13/0006H02J13/00016H02J13/00034H02J3/001H02J2203/10
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,611,219
App. No.
17/340,664
Granted
Mar 21, 2023
Kind
B2
Abstract

Systems include one or more critical datacenter connected to behind-the-meter flexible datacenters. The critical datacenter is powered by grid power and not necessarily collocated with the flexboxes, which are powered “behind the meter.” When a computational operation to be performed at the critical datacenter is identified and determined that it can be performed at a lower cost at a flexible datacenter, the computational operation is instead routed to the flexible datacenters for performance. The critical datacenter and flexible datacenters preferably shared a dedicated communication pathway to enable high-bandwidth, low-latency, secure data transmissions.

Claims (44)

1. A system comprising

a flexible datacenter comprising:

a first power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to a power grid,

a first power distribution system, and

a first plurality of computing systems powered by the first power input system via the first power distribution system;

a flexible datacenter control system, wherein the flexible datacenter control system is configured to modulate power delivery to the first plurality of computing systems based on one or more monitored power system conditions or an operational directive;

a critical datacenter comprising:

a second power input system configured to receive power from the power grid,

a second power distribution system, and

a second plurality of computing systems powered by the grid-power input system via the second power distribution system;

a communication link between the flexible datacenter and the critical datacenter; and

a routing control system configured to (i) identify a computational operation to be performed, (ii) determine whether or not to assign the computational operation to the flexible datacenter, and (iii) based on a determination to assign the computational operation to the flexible datacenter, cause the computational operation to be sent to the flexible datacenter via the communication link,

wherein configured to determine whether or not to assign the computational operation to the flexible datacenter via the communication link comprises configured to determine whether the flexible datacenter has enough computing resources to satisfy the computational operation.

2. The system of claim 1 , wherein the routing control system comprises a remote master control system.

3. The system of claim 2 , wherein the remote master control system is not collocated with the flexible datacenter.

4. The system of claim 2 , wherein the remote master control system is not collocated with the critical datacenter.

5. The system of claim 1 , wherein the routing control system is configured to reassign one or more computational operations from the critical datacenter for completion by the flexible datacenter.

6. The system of claim 1 , wherein the routing control system and a critical datacenter control system are a single control system.

7. The system of claim 1 , wherein configured to determine whether the flexible datacenter has enough available computing resources to satisfy the computational operation comprises configured to analyze workloads of the flexible datacenter and identify whether the flexible datacenter has sufficient computing resources to process the computational operation.

8. The system of claim 1 , wherein configured to determine whether to route the computational operation to the flexible datacenter via the communication link comprises configured to determine behind-the-meter power availability at the flexible datacenter.

9. The system of claim 1 , wherein configured to determine whether to route the computational operation to the flexible datacenter via the communication link comprises configured to determine whether a ramp-up condition associated with the flexible datacenter is met.

10. The system of claim 9 , wherein the ramp-up condition comprises one or more of a fully online status or a fully offline status.

11. A system comprising

a plurality of flexible datacenters, each flexible datacenter comprising:

a first power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to a power grid,

a first power distribution system, and

a first plurality of computing systems powered by the first power input system;

a flexible datacenter control system, wherein the flexible datacenter control system is configured to modulate power delivery to at least one of the first plurality of computing systems based on one or more monitored power system conditions or an operational directive;

a critical datacenter comprising:

a second power input system,

a second power distribution system, and

a second plurality of computing systems powered by the second power input system via the second power distribution system;

a communication link between the plurality of flexible datacenter and the critical datacenter; and

a routing control system configured to (i) receive a computational operation, (ii) determine whether or not to route the computational operation to a flexible datacenter of the plurality of flexible datacenters, (iii) based on a determination to route the computational operation to a flexible datacenter of the plurality of flexible datacenters, determine a specific flexible datacenter of the plurality of flexible datacenters to which to route the computational operation, and (iv) cause the computational operation to be sent to the specific flexible datacenter via the communication link;

wherein configured to determine a specific flexible datacenter in the plurality of flexible datacenters to which to route the computational operation comprises determining which of the plurality of flexible datacenters has enough computing resources available to satisfy the computational operation.

12. The system of claim 11 , wherein the routing control system comprises a remote master control system.

13. The system of claim 12 , wherein the remote master control system is not collocated with the flexible datacenter.

14. The system of claim 12 , wherein the remote master control system is not collocated with the critical datacenter.

15. The system of claim 11 , wherein configured to determine which of the plurality of flexible datacenters has enough computing resources available to process the computational operation comprises configured to analyze workloads of the plurality of the flexible datacenters and to identify one or more specific flexible datacenters having sufficient computing resources to process the computational operation.

16. The system of claim 11 , wherein the routing control system is configured to reassign one or more computational operations from the critical datacenter for completion by one or more flexible datacenters of the plurality of flexible datacenters.

17. The system of claim 11 , wherein configured to cause the computational operation to be sent to one or more flexible datacenters of the plurality of flexible datacenters via the communication link comprises configured to divide the computational operation among multiple flexible datacenters of the plurality of flexible datacenters.

18. The system of claim 11 , further comprising a remote master control system communicatively coupled to the flexible datacenter via a second communication link, wherein the computational operation does not travel on the second communication link.

19. The system of claim 11 , wherein configured to determine a specific flexible datacenter in the plurality of flexible datacenters to which to route the computational operation to comprises configured to determine the specific flexible datacenter to route the computational operation to based on behind-the-meter power availability to the plurality of flexible datacenters.

20. The system of claim 11 , wherein configured to determine which of the plurality of flexible datacenters has enough computing resources available to satisfy the computational operation comprises configured to determine whether a ramp-up condition and/or a ramp-down condition is associated with one or more of the flexible datacenters.

Continuity (2)
Continuation 16132062 · Sep 14, 2018
Related Publication 20210296893A1 · Sep 23, 2021
Cited By (8)
US 12,204,945 US 12,210,911 US 12,294,217 US 12,307,301 US 12,362,563 US 12,573,855 US 12,646,939 US 12,711,560